Knife River and the Montana Department of Transportation have released a construction update for the week of Aug. 19 – Aug 26.

Knife River will be finishing the gravel surfacing on Meade Ave from Towne St to Dodge St. in preparation for pavement. Expect paving operation starting as early as Aug. 22. We will be working with the school system and city to ensure access to the school for the buses either along Meade Avenue or River Avenue.

During the paving operation be prepared for full and partial closures along Towne Street. We will provide more detailed information early next week, as the schedule gets finalized.

Knife River’s concrete crew will continue to work on getting the concrete curb and gutter and sidewalks replaced along Towne Street.

They will try to work on one side of the street at a time, but please watch for equipment and workers at all intersections.